MRP/Item Availability Using Commits from Closed Work Order

$
0
0
I'm seeing a scenario where we have a MRP commitment for a firm work order that is "closed". Once our manufacturing facility completes a work order, it is moved to a status 95 - Manufacturing complete. The quantity committed in F3111 still shows an amount, even though the work order has been issued. I can see the quantity in both Item Availability and MRP. Is there some place we need to go set up the statuses used for commitments for work orders?