MRP Priority for multiple sources of demand on same date

$
0
0
Hello everyone, and apologies in advance if my question is difficult to understand or plain dumb, but I will try and explain the issue we are having in detail.
So my question is regarding the order in which component requirements are considered to be met for demand sources on the same date. So for example, if I have 100 of component x in stock, and 3 orders (call then 1,2 and 3) using 200, 200, and 100 of this component on the same day, which of these orders will have 100 units covered by...

Read more