Here is our scenario. A finished good requires a test after the work order is completed - so maybe a five day micro test. Our production planners want a way so they can plan the completion date to be before the testing is done. For instance, a work order is scheduled for barbeque sauce. Currently, MRP prompts for a completion date of let's say 7/31. However, the 3-day Spice-O-Meter test needs to be applied after completion. So, if we follow MRP's completion date, we will be three days...